Progress at our site on Earlstree Industrial Estate in Corby, where we are undertaking the ground works and civils.

- Ground stabilisation and ground engineering completed
- Foundations for Unit 1 & 2 completed, steel now erected and buildings taking shape
- Unit 1 & 2 yard slabs being poured and finished, working with H&G Construction UK Limited
- Carpark and access roads under way with base course of tarmac going down thanks to TriAgg
- Progress on drainage and services continue with works to be completed for client fit out specifications of unit 2

A huge thank you to everyone’s hard work so far, keep it up all!